LH series of standard parameter table (500T)
Items | Unit | Specification |
Hydraulic Working Pressure | MPa | 14 |
Clamping Force | KN | 5000 |
Space Between Tie Bars | mm | 760*660 |
Tie Bar Diameter | mm | ¢140 |
Die Opening Stroke | mm | 450 |
Injecction Force(intensify) | KN | 450 |
Plunger launch distance | mm | 250 |
Injection position | mm | 0 -- 220 |
Plunger Diameter | mm | ¢70----¢90 |
Injection Stroke | mm | 580 |
Casting pressure (intensify) | MPa | 135/117/92 |
Casting Fiange Protrusion | mm | 15 |
Casting Fiange Diameter | mm | 130 |
(40Mpa) Max Casting Area Under40Mpa | CM2 | 1209 |
lnjection Weight(Al) | Kg | 6.9 |
Die Height(Min--Max) | mm | 300~800 |
Ejector Force | KN | 240 |
Ejector Steoke | mm | 140 |
Motor Capacity | Kw | 22 |
Machine Dimensions (L*W*H) | m | 7.7*2.1*3.1 |
Referential Machine Weight For Uplifting | T | 20 |
Oil Tank Capacity | L | 1200 |
Longhua and the Chinese Academy of Sciences jointly research and develop and are committed to creating a new type of intelligent energy-saving die casting machine. There is no need to purchase a servo motor separately, but it has the same energy saving effect as a servo motor! Our customers save costs and win-win cooperation!
1. For customers who purchase Longhua products, we have trained professional engineers to enable them to independently operate,
use and maintain Longhua products; 2. To answer technical questions in a timely manner, the company can send people to the user
site for assistance and guidance in time; 3. Provide technical guidance when users need new equipment or expansion
(reconstruction) construction; 4. After the company's products are upgraded, priority should be given to the replacement of the
previous users as required.
use and maintain Longhua products; 2. To answer technical questions in a timely manner, the company can send people to the user
site for assistance and guidance in time; 3. Provide technical guidance when users need new equipment or expansion
(reconstruction) construction; 4. After the company's products are upgraded, priority should be given to the replacement of the
previous users as required.