Installation technology of aluminum veneer ceiling
Aluminum veneer ceiling installation process, aluminum veneer ceiling is everywhere, and is widely used in the interior decoration, in the decorative effect is very good, in addition to aluminum veneer ceiling products are very important, aluminum veneer ceiling installation process is also very important, the correct installation in the decorative effect is better, in the details more refined.
1. Weak line: according to the floor elevation horizontal line, according to the design elevation, along the elevation horizontal line of the ceiling around the wall, and find out the center point of the room, and along the elevation horizontal line of the ceiling, with the center point of the room as the center, draw the keel partition position line on the wall.
2. Install the main keel suspender: after snapping the ceiling elevation horizontal line and keel position line, determine the elevation of the lower end of the suspender, install the pre-processed suspender, and fix the suspender on the ceiling with the diameter 8 expansion bolt. The diameter of the suspender is 8 round steel, and the spacing of suspender is controlled within 1200mm.
3. Installation of the main keel: C38 light steel keel is generally selected as the main keel, and the spacing is controlled within 1200mm. During the installation, the lifting parts matched with the main keel are used to connect with the suspender.
4. Install side keel: fix 25x25m paint keel with cement nails around the wall according to the requirements of ceiling clear height, and the spacing between cement nails shall not be greater than 300mm
5. Installation of the secondary keel: according to the specification and size of the aluminum ceiling, install the secondary keel matched with the board, and the secondary keel is hung on the main keel by hanging parts. When the length of the secondary keel needs to be extended by several pieces, use the connecting piece of the secondary keel. While hanging the secondary keel, connect the opposite ends, straighten them first and then fix them.
Aluminum Veneer for Ceiling
6. Installation of metal plate: during the installation of an aluminum ceiling, a reference line shall be drawn perpendicular to the direction of the secondary keel in the middle of the assembly area, and the reference line shall be aligned for installation on both sides. During installation, handle with care. Press both sides of the square plate in the sequence of flanging parts, and then push it tight after it is clamped into the keel.