Real prject-- Slaughterhouse use high temperature heat pump + solar energy+ electric steam at the sa

   date:2020-10-27     browse:0    comments:0    

high temperature heat pump

Confirmation of Installation Location of Main Equipment

Considering that the slaughterhouse is equipped with a cold storage, and the air conditioning units in the cold storage have special equipment rooms. Although there are two large windows and no glass, the temperature of the air conditioning equipment in the cold storage is high all the year round, and the location of the equipment room is enough, while the location near the high temperature pool is narrow. In order to make full use of the heat of the air conditioning equipment in the cold storage, the temperature of the air conditioning equipment is high. To maximize the energy-saving effect, through communication with Party A, 4 tons of heat preservation water tank and air energy high temperature machine were installed in the air conditioning equipment room of the cold storage.

 

This can not only make hot water from the heat of the air conditioning equipment in the cold storage, but also cool the air conditioning equipment in the cold storage when the air can work, making the cold storage equipment more energy-saving.

 

Because of the heavy ammonia gas in the slaughterhouse, most of the workshops are made of resin tiles with insufficient load-bearing capacity and can not install solar energy. Only the cold storage and meat shelf workshops adopt double-layer heat preservation colored steel sheet herringbone roof. Because the workshops need to hang pigs, the load-bearing capacity is very good, and the total area of the roof is more than 500 square meters, the location is enough, so 400. The solar energy of the connecting box of the branch project is installed on the herringbone roof.

 

In order to reduce the steam temperature loss and minimize the distance between the steam generator and the high temperature pool, the steam generator is placed in the original boiler room of the outer wall of the high temperature pool. DN25 hot galvanized steel pipe is used for steam supply. The pipeline is not insulated or insulated by high temperature asbestos. It should be noted that rubber and plastic can not be used for insulation and will be scalded. Steam solenoid valves are also installed in the steam supply pipeline and manually bypass ball valves are made. Water temperature probes are placed in the pool, and the steam solenoid valves are controlled by temperature controllers.


 
Article Source: Real prject-- Slaughterhouse use high temperature heat pump + solar energy+ electric steam at the sa